Smart Meter Deployment and the Application of Time-of-use Pricing
On August 4, 2010, the Board issued a determination (EB-2010-0218) under section 1.2.1 of the Standard Supply Service Code to mandate time-of-use pricing for regulated price plan customers. The determination included new monthly reporting requirements to enable the Board to monitor distributors’ progress in relation to the implementation of TOU pricing.
Smart Meter Deployment and Mandatory Implementation of Time-of-use Pricing
Monitoring Distributor Progress
The Board has established through the issuance of the Determination processes to monitor the progress of distributors and SME.
- OEB Monthly Monitoring Reports (last updated Apr 18-12) - CLICK TO EXPAND
- August 2010 (posted Oct 25-10)
- September 2010 (posted Nov 12-10)
- October 2010 (posted Dec 9-10)
- November 2010 (posted Jan 6-11)
- December 2010 (posted Feb 28-11)
- January 2011 (posted Mar 17-11)
- February 2011 (posted Mar 31-11)
- March 2011 (posted May 3-11)
- April 2011 (posted Jun 3-11)
- May 2011 (posted Jun 29-11)
- June 2011 (posted Aug 2-11)
- July 2011 (posted Nov 4-11)
- August 2011 (posted Nov 8-11)
- September 2011 (posted (Nov 28-11)
- October 2011 (posted (Dec 1-11)
- November 2011 (posted Feb 8-12)
- December 2011 (posted Mar 13-12)
- January 2012 (posted Apr 18-12)
- February 2012 (posted Apr 18-12)
- Distributor Monthly Filings
- SME Monthly Filings (last updated Apr 18-12) - CLICK TO EXPAND
- August 2010 (posted Oct 25-10)
- September 2010 (posted Nov 12-10)
- October 2010 (posted Dec 9-10)
- November 2010 (posted Jan 6-11)
- December 2010 (posted Feb 28-11)
- January 2011 (posted Mar 17-11)
- February 2011 (posted Mar 31-11)
- March 2011 (posted May 3-11)
- April 2011 (posted Jun 3-11)
- May 2011 (posted Jun 29-11)
- June 2011 (posted Aug 2-11)
- July 2011 (posted Nov 4-11)
- August 2011 (posted Nov 8-11)
- September 2011 (posted Nov 28-11)
- October 2011 (posted Dec 1-11)
- November 2011 (posted Feb 8-12)
- December 2011 (posted Mar 13-12)
- January 2012 (posted Apr 18-12)
- February 2012 (posted Apr 18-12; revised Apr 25-12)
The Board has established processes to monitor distributor’s smart meter investments.
Updates
|
Date |
Issue / Document |
|---|---|
|
Feb 1-12 |
The Board has issued a letter to all licensed electricity distributors giving direction on ending the monthly reporting requirements related to smart meters and time of use implementation. |
|
Nov 22-10 |
Board staff have made a correction to Appendix A of the Board’s October 26th letter regarding new reporting requirements related to smart meter investments. |
|
Oct 26-10 |
The Board has issued a letter to all licensed electricity distributors on new reporting requirements related to smart meter investments. |
|
Sep 7-10 |
The Board has issued a letter to the Independent Electricity System Operator on new reporting requirements for submitting monthly filings as to its readiness, performance, and progress of distributor integration with respect to smart meter deployment and mandatory implementation of time-of-use pricing. |
|
The Board has issued a letter to all licensed electricity distributors on new reporting requirements for submitting monthly filings on smart meter deployment and the application of time-of-use pricing. |
|
|
Aug 4-10 |
The Board has issued a final determination under section 1.2.1 of the Standard Supply Service Code to mandate time-of-use pricing for regulated price plan customers: |
Smart Meter Deployment and the Application of Time-of-use Pricing Quarterly Reporting for the Period from June 2009 – June 2010
In June 2009, the Board requested information from distributors about their plans for meter installation, MDM/R meter enrollment and implementation of time-of-use (“TOU”) pricing. These “baseline” filings included monthly plans until June 2011 for these three activities, and a quarterly filing of actions taken by each distributor to achieve the timelines set out in its baseline plan.
Updates
|
Date |
Issue / Document |
|---|---|
|
Aug 12-10 |
The Board has issued its 2010 Second Quarter Monitoring Report on Smart Meter Deployment and Time-of-use Pricing. |
|
May 6-10 |
The Board has issued its 2010 First Quarter Monitoring Report on Smart Meter Deployment and Time-of-use Pricing. |
|
Mar 24-10 |
The Board has issued a letter to all licensed distributors outlining a new online process for submitting quarterly filings on smart meter deployment and the application of time-of-use pricing. |
|
Feb 25-10 |
The Board has issued its 2009 Fourth Quarter Monitoring Report on Smart Meter Deployment and Time-of-use Pricing.
|
|
Nov 23-09 |
In accordance with Board requirements, on October 10th 2009 electricity distributors filed a first quarterly report on smart meter deployment and the application of time-of-use pricing. The Board has prepared a monitoring report based on a comparison of these filings with the baseline data submitted in July. In addition, the Board has sent a letter to all electricity distributors to clarify the original reporting requirements.
|
|
Jun 26-09 |
The Board issued a letter to all licensed electricity distributors on new reporting requirements related to smart meter deployment and the application of time-of-use pricing. |
Smart Meter Deployment and Application of Time-of-use Pricing Reports and Filings
Page last updated 2012-04-25